Media Contact: John Lisle at (202) 671-2004
The District of Columbia Department of Transportation (DDOT) is scheduling bridge rehabilitation and demolition work on the 9th Street, SW Bridge over I-395 (Southwest Freeway) next week. This is a continuation of work begun this week and will require temporary lane closures on Interstate 395 from Monday, February 9 to Friday, February 13.
The demolition work will require the closure of a single lane on I-395 under the 9th Street Bridge from 10 am to 3 pm each day. The lane closure will be on either the northbound or southbound side depending on the needs of the contractor.
Additional lane closures will occur from 8 pm to 5 am each night on either the northbound or southbound side of the roadway.
Variable message signs will be in place to alert motorists and direct them around the lane closures, but traffic delays are possible and drivers should use caution when traveling through the work zones.
We apologize for any inconvenience. DDOT is in the process of completely rehabilitating both the 9th and 10th Street, SW Bridges. This is a year long project that began last November.